Nearshore cable handling for offshore windfarm development

Three tensioners in line over 3km beach to pull in export cables for the world’s largest offshore wind farm

Benefits

  • Versatile rental fleet provided three tensioner systems suited to cable and beach location
  • Technical support and advice throughout the project
  • Equipment with software capable of data logging all operations to ensure cable integrity
  • One subcontractor to deliver complete solution

Challenge

  • Hornsea One is to be the world’s largest offshore windfarm when commissioned
  • The client was required to perform the shore approach to lay three cables from the CLV Ndurance cable laying vessel at 3.6km offshore to an onshore beach site
  • Three cables were to be transferred from the vessel to the shore via a jack-up and two pontoons where tensioners were stationed
  • Performance of each machine was to be logged to ensure cable integrity was not compromised. The work was required to meet a tight mobilisation schedule and timeline for completion.

Solution

  • One 15Te tensioner was installed on a jack- up which involved designing some of the jack-up outrigger structure
  • Two 10Te tensioners were installed on separate Linkflote pontoons which required design and supply of all the sea fastenings
  • Manual and digital logs were taken for the activities during the pull ins with Sparrows PLC engineers implementing equipment upgrades to ensure data logging was performed
  • Bespoke track pads were installed onto each of the tensioners with a special material to ensure higher friction was achievable and track pad to cable contact pressures were lower than the cables design limitations
  • As well as supply of the tensioners, experienced Sparrows operators managed the equipment throughout the project.
More Offshore Energy Case Studies