Three tensioners in line over 3km beach to pull in export cables for the world’s largest offshore wind farm
Benefits
- Versatile rental fleet provided three tensioner systems suited to cable and beach location
- Technical support and advice throughout the project
- Equipment with software capable of data logging all operations to ensure cable integrity
- One subcontractor to deliver complete solution
Challenge
- Hornsea One is to be the world’s largest offshore windfarm when commissioned
- The client was required to perform the shore approach to lay three cables from the CLV Ndurance cable laying vessel at 3.6km offshore to an onshore beach site
- Three cables were to be transferred from the vessel to the shore via a jack-up and two pontoons where tensioners were stationed
- Performance of each machine was to be logged to ensure cable integrity was not compromised. The work was required to meet a tight mobilisation schedule and timeline for completion.
Solution
- One 15Te tensioner was installed on a jack- up which involved designing some of the jack-up outrigger structure
- Two 10Te tensioners were installed on separate Linkflote pontoons which required design and supply of all the sea fastenings
- Manual and digital logs were taken for the activities during the pull ins with Sparrows PLC engineers implementing equipment upgrades to ensure data logging was performed
- Bespoke track pads were installed onto each of the tensioners with a special material to ensure higher friction was achievable and track pad to cable contact pressures were lower than the cables design limitations
- As well as supply of the tensioners, experienced Sparrows operators managed the equipment throughout the project.